Network Upgrade Details
This page contains information about the network upgrade progress for the Gregory Hall building.
|
|
Gregory Hall 810 S. Wright St.,
Urbana |
Note: A number of factors affect the scope of a building's network upgrade, including square footage, the future networking needs of the units housed in the building, and the original state of the building's network infrastructure.
Statistics |
|
CERs: |
3 |
| New cabling drops: | 437 |
| New Cat6 jacks: | 1319 |
| UIUCnet Wireless access points: | 36 |
| 100 Mbps Ethernet switch ports: | 1027 |
| 1 Gbps Ethernet switch ports: | 52 |
General building data |
|
Upgrade year: |
2005 |
College/Unit: |
Communications |
Electronics-only or
full upgrade: |
Full upgrade |
Network Design Office (NDO) contact: |
Josh Reeley |
College/Unit building
upgrade coordinator: |
|
Design milestones |
(MM-DD-YYYY) |
| Drawings issued: | 03-11-2005 |
| Drawings returned: | 05-03-2005 |
| Plant Engineering started: | 07-11-2005 |
| Plant Engineering finished: | |
| Drawings to F & S: | |
CER milestones |
|
| CER rooms identified on: | 08-12-2005 |
| CER rooms approved on: | 01-10-2006 |
Construction milestones |
|
| Construction started: | |
| Electronics order to Purchasing: | |
| Electronics received: | |
| Construction completed: |