Network Upgrade Details

This page contains information about the network upgrade progress for the Gregory Hall building.

Building photo

Gregory Hall

810 S. Wright St., Urbana
Building number: 0043

Back to building overview


Note: A number of factors affect the scope of a building's network upgrade, including square footage, the future networking needs of the units housed in the building, and the original state of the building's network infrastructure.

Statistics

 
CERs:
3
New cabling drops: 437
New Cat6 jacks: 1319
UIUCnet Wireless access points: 36
100 Mbps Ethernet switch ports: 1027
1 Gbps Ethernet switch ports: 52

General building data

 
Upgrade year:
2005
College/Unit:
Communications 
Electronics-only or full upgrade:
Full upgrade
Network Design Office
(NDO) contact:
Josh Reeley
College/Unit building
upgrade coordinator:

Design milestones

(MM-DD-YYYY)
Drawings issued: 03-11-2005
Drawings returned: 05-03-2005
Plant Engineering started: 07-11-2005
Plant Engineering finished:
Drawings to F & S:

CER milestones

 
CER rooms identified on: 08-12-2005
CER rooms approved on: 01-10-2006

Construction milestones

 
Construction started:
Electronics order to Purchasing:
Electronics received:
Construction completed:

Back to building overview