Network Upgrade Details
This page contains information about the network upgrade progress for the Foellinger Auditorium building.
|
|
Foellinger Auditorium 709 S. Mathews Ave.,
Urbana |
Note: A number of factors affect the scope of a building's network upgrade, including square footage, the future networking needs of the units housed in the building, and the original state of the building's network infrastructure.
Statistics |
|
CERs: |
1 |
| New cabling drops: | 48 |
| New Cat6 jacks: | 90 |
| UIUCnet Wireless access points: | 17 |
| 100 Mbps Ethernet switch ports: | 90 |
| 1 Gbps Ethernet switch ports: | 14 |
General building data |
|
Upgrade year: |
2006 |
College/Unit: |
Provost |
Electronics-only or
full upgrade: |
Full upgrade |
Network Design Office (NDO) contact: |
|
College/Unit building
upgrade coordinator: |
|
Design milestones |
(MM-DD-YYYY) |
| Drawings issued: | 02-03-2006 |
| Drawings returned: | 02-07-2006 |
| Plant Engineering started: | 02-10-2006 |
| Plant Engineering finished: | |
| Drawings to F & S: | |
CER milestones |
|
| CER rooms identified on: | 03-03-2006 |
| CER rooms approved on: | 02-07-2006 |
Construction milestones |
|
| Construction started: | |
| Electronics order to Purchasing: | |
| Electronics received: | |
| Construction completed: |